IBOV 166,376.43 ▼ 0.69% COLCAP 2,452.46 — — IPC MEX 68,713.60 ▼ 0.64% MERVAL 2,848,945 — — USD/BRL5.95▲ 0.24% USD/MXN19.18▲ 0.49% USD/CLP1,022▲ 0.52% USD/COP3,500▲ 4.25% USD/PEN3.45▲ 0.16% USD/ARS1,580▲ 0.93% USD/UYU40.61▲ 3.16% USD/PYG6,212▲ 2.34% USD/BOB11.64▲ 2.55% USD/DOP59.48▼ 0.87% USD/CRC441.73▲ 2.68% USD/GTQ7.64▲ 3.22% USD/HNL26.89▲ 3.31% USD/NIO36.62▲ 0.34% USD/VES913.46▼ 0.45% USD/PAB1.00— 0.00% USD/BZD2.00— 0.00% USD/JMD157.59▲ 2.60% USD/TTD6.70▲ 2.00% EUR/BRL6.53▲ 1.21% BRENT 89.61 ▼ 2.58% WTI 83.12 ▼ 0.11% IRON ORE 161.91 — — COPPER 5.47 ▼ 2.70% GOLD 3,523 ▼ 4.41% SILVER 40.99 ▼ 7.51% SOY 1,221 ▲ 1.08% CORN 448.75 ▲ 2.22% WHEAT 593.00 ▲ 2.55% COFFEE 268.70 ▼ 4.73% SUGAR 17.07 ▼ 0.52% ORANGE JUICE 129.25 ▼ 2.49% COTTON 79.30 ▲ 4.41% COCOA 5,294 ▲ 4.56% BEEF 227.95 ▲ 2.29% CATTLE 335.43 ▼ 0.78% LITHIUM 52.12 ▼ 4.07% PETR4 42.67 ▼ 1.16% VALE3 58.48 ▼ 0.88% ITUB4 40.07 ▼ 0.30% BBDC4 13.83 ▼ 1.78% ABEV3 16.08 ▲ 0.06% BBAS3 14.30 ▲ 1.27% B3SA3 14.28 ▼ 0.14% WEGE3 51.13 ▼ 0.49% PRIO3 60.20 ▼ 2.70% SUZB3 55.32 ▼ 0.50% RENT3 28.86 ▼ 2.00% AZZA3 14.63 ▼ 7.29% CSAN3 3.08 ▼ 1.60% RAIZ4 15.00 ▼ 10.71% PCAR3 3.23 ▲ 8.03% GMAT3 4.18 ▲ 3.21% PSSA3 43.96 ▼ 1.57% CVCB3 0.72 ▼ 7.69% POSI3 3.37 ▲ 6.31% SLCE3 17.53 ▼ 1.96% NATU3 4.48 ▼ 6.28% BRKM5 2.60 ▼ 1.14% RANI3 8.01 ▼ 0.74% IBOV 166,376.43 ▼ 0.69% COLCAP 2,452.46 — — IPC MEX 68,713.60 ▼ 0.64% MERVAL 2,848,945 — — USD/BRL 5.95 ▲ 0.24% USD/MXN 19.17 ▲ 0.44% USD/CLP 1,022 ▲ 0.52% USD/COP 3,502 ▲ 4.34% USD/PEN 3.45 ▲ 0.15% USD/ARS 1,580 ▲ 0.93% USD/UYU 40.61 ▲ 3.16% USD/PYG 6,212 ▲ 2.34% USD/BOB 11.64 ▲ 2.55% USD/DOP 59.48 ▼ 0.87% USD/CRC 441.73 ▲ 2.68% USD/GTQ 7.64 ▲ 3.22% USD/HNL 26.89 ▲ 3.31% USD/NIO 36.62 ▲ 0.34% USD/VES 913.46 ▼ 0.45% USD/PAB 1.00 — 0.00% USD/BZD 2.00 — 0.00% USD/JMD 157.59 ▲ 2.60% USD/TTD 6.70 ▲ 2.00% EUR/BRL 6.53 ▲ 1.21% BRENT 89.61 ▼ 2.58% WTI 83.12 ▼ 0.11% IRON ORE 161.91 — — COPPER 5.47 ▼ 2.70% GOLD 3,523 ▼ 4.41% SILVER 40.99 ▼ 7.51% SOY 1,221 ▲ 1.08% CORN 448.75 ▲ 2.22% WHEAT 593.00 ▲ 2.55% COFFEE 268.70 ▼ 4.73% SUGAR 17.07 ▼ 0.52% ORANGE JUICE 129.25 ▼ 2.49% COTTON 79.30 ▲ 4.41% COCOA 5,294 ▲ 4.56% BEEF 227.95 ▲ 2.29% CATTLE 335.43 ▼ 0.78% LITHIUM 52.12 ▼ 4.07% PETR4 42.67 ▼ 1.16% VALE3 58.48 ▼ 0.88% ITUB4 40.07 ▼ 0.30% BBDC4 13.83 ▼ 1.78% ABEV3 16.08 ▲ 0.06% BBAS3 14.30 ▲ 1.27% B3SA3 14.28 ▼ 0.14% WEGE3 51.13 ▼ 0.49% PRIO3 60.20 ▼ 2.70% SUZB3 55.32 ▼ 0.50% RENT3 28.86 ▼ 2.00% AZZA3 14.63 ▼ 7.29% CSAN3 3.08 ▼ 1.60% RAIZ4 15.00 ▼ 10.71% PCAR3 3.23 ▲ 8.03% GMAT3 4.18 ▲ 3.21% PSSA3 43.96 ▼ 1.57% CVCB3 0.72 ▼ 7.69% POSI3 3.37 ▲ 6.31% SLCE3 17.53 ▼ 1.96% NATU3 4.48 ▼ 6.28% BRKM5 2.60 ▼ 1.14% RANI3 8.01 ▼ 0.74%
since 2009
Friday, November 20, 2026

Life & Society Real Estate

More Funding is Needed for the Construction of Rio’s Metro Line 4

By · · 3 min read
Brazil, Brazil News, Rio de Janeiro, Rio, Linha 4 Metro, Metro Extension, Zona Sul, South Zone, West Zone, Barra da Tijuca, São Conrado
The German Tunnel Boring Machine (TBM), known as the “Tatuzão”, which has been used in the construction of the tunnel of the new Metro Line 4, photo courtesy of Linha 4.

By Georgia Grimond, Senior Contributing Reporter

RIO DE JANEIRO, BRAZIL – The new stretch of metro line, Linha 4, that is being constructed to link Zona Sul (South Zone) with Barra da Tijuca in the Zona Oeste (West Zone) may not be ready in time for the 2016 Rio Olympics unless R$1 billion is given by the federal government for the project.

RT
Ask Rio Times
17 years of Latin America reporting, on demand.
Open the full Ask Rio Times →

Carlos Roberto Osório, Rio’s transport secretary, said R$445 million in funding from the BNDES national development bank had already been approved by the treasury and was due to be released his month.

He requested a further R$500 million in order to complete the non-Olympic sections of the works (Gávea station) and the connection between lines 1 and 4.

“Obviously we want to finish the work as a whole. Therefore, the governor has signaled the need for R$1 billion,” said Osório.

The opening of the new metro line is now scheduled for July 1st 2016, in time for the beginning of the Olympic Games in the city on August 5th. Osório was optimistic that the funding would be supplied but emphasized that without it the opening date may not be met.

The LatAm Brief

One email, every weekday morning. What moved in Latin American markets, politics and expat life.

Yesterday’s subject line: “Mexico's election chief won't be named before late January”

“We are awaiting the arrival of President Dilma Rousseff in Rio to discuss the release of funds for completion of construction of Metro Line 4. About R$500 million have been requested from the BNDES to complete it in time the Olympics,” state governor Luiz Fernando Pezão said last week.

Brazil, Brazil News, Rio de Janeiro, Rio, Linha 4 Metro, Metro Extension, Zona Sul, South Zone, West Zone, Barra da Tijuca, São Conrado
The new station at São Conrado will be the second largest on the new metro line, photo courtesy of Linha 4.

Six new stations are being constructed as part of the Linha 4 works – Nossa Senhora da Paz, Jardim de Alah, Antero de Quental, Gávea, São Conrado and Jardim Oceânico – linking for the first time Zona Sul with Barra da Tijuca where the main Olympic Park will be.

The new metro line will carry more that 300,000 people today, freeing the roads of close to 2,000 vehicles per hour at peak times. A journey from Barra to Ipanema will take thirteen minutes and thirty four minutes to Centro.

However passengers who pick up the line on the new extension will have to change trains at General Osório in Ipanema in order to continue their journey to Centro as the connection will not have been completed by July next year. After a testing phase, passengers should be able to make the journey continuously from the beginning of 2017.

The two officials visited a section of the new track last, Tuesday, December 15th. They travelled between São Conrado and Barra da Tijuca. Works are 83 percent complete, with only seven hundred meters of excavation remaining to be done. Sao Conrado station, the second largest on the line, is in the final stage of completion.

During the excavation of rock on the stretch between Barra da Tijuca and Leblon, 3,865 tons of explosives have been used, the equivalent to the fireworks needed for 161 New Year’s Eve celebrations in Copacabana. Close to 256,000 m3 of concrete were also used in the tunnel, the same amount as would have been used to build 3.2 Maracanã stadiums in 1950.

This article was produced by The Rio Times’ automated AI newsroom. Editorial responsibility: Matthias Camenzind, Publisher and Editor-in-Chief. The Rio Times also runs Ask Rio Times, which answers from 100,000+ of our own articles, the daily Latin America Power Map, and prediction-market odds on elections and markets.. How we use AI · Report an error

Living in or visiting Rio de Janeiro? See this month's events and our Rio de Janeiro city guide with rents, safety and upcoming concerts.

The Rio Times · Power Map
See who really holds power in Latin America
Click to open the Power Map →

Brazil runoff date: Sunday, October 25, poll closing times and when results start · Brazil runoff polls: Flávio 51%, Lula 49% · Kalshi and Polymarket odds

Rotate for Best Experience

This report is optimized for landscape viewing. Rotate your phone for the full experience.