Kenya’s Oldest Geothermal Plant Is Rebuilt
A plant that has run for more than four decades gets a second life, but by our reading the extra power is small next to Kenya’s fast-rising demand.

Kenya · Energy
Kenya’s oldest geothermal power station is back on the grid after a three-year rebuild. Peter Njenga, chief executive of KenGen (Kenya Electricity Generating Company, the state-controlled power producer), said in Naivasha, a lakeside town near the plant, on Wednesday 25 November 2026 that the works at Olkaria I are complete.
Geothermal plants turn underground steam into electricity, and the rebuild lifts Olkaria I from 45 to about 63 megawatts (MW). Njenga said President William Ruto is due to commission the plant on Monday 7 December 2026.
Key Facts
- Who. KenGen, Kenya’s state-controlled power producer, led by chief executive Peter Njenga.
- What. Olkaria I rebuilt: capacity rises from 45 MW to 63.3 MW.
- Why. KenGen aims to extend the plant’s life by over 25 years; net gain 18.3 MW.
- Next. President William Ruto is due to commission the plant on Monday 7 December 2026.
- As of. 25 November 2026, 12:30 UTC.
A plant that has run for more than four decades gets a second life, but by our reading the extra power is small next to Kenya’s fast-rising demand.
What KenGen Says It Has Finished
“We have completed the rehabilitation works on the oldest Olkaria I power plant, which will boost power generation from the initial 45 MW to 63 MW,” Njenga said on 25 November. He said the plant is now in trials.
Olkaria I lies in the Olkaria geothermal field near Naivasha, in Nakuru County in Kenya’s Rift Valley. KenGen’s project page calls it Africa’s first geothermal plant and dates it to 1980, while this week’s statement gives 1981; the aim of the rebuild is to raise installed capacity to 63.3 MW.
The plant had been shut for the works by 21 May 2023, a KenGen manager said then. Japan’s Toshiba Energy Systems and Solutions and SEPCO3, a subsidiary of the Chinese state-owned group China Power Construction, were contracted for new turbines and generators, KenGen said in March 2024.
Why Two Figures Circulate
Njenga also said that day KenGen had “injected an extra 63.3mw into the national grid.” Both figures describe the same plant, whose new total capacity on KenGen’s project page is 63.3 MW.
By our calculation, the gain over the old 45 MW plant is 18.3 MW. In our reading, 63.3 MW is “extra” only against the plant’s output while it was shut.
The paper trail lags the announcement. KenGen’s undated project page, as read on 25 November 2026, still shows the work as “83% complete”, while a KenGen financial report in July 2026 put it at 92%, so by our reading the page has not been updated.
KenGen called the project complete at its annual general meeting on Thursday 29 October 2026. The plant’s three generating units returned in stages, Unit 3 in May 2026 and Unit 2 by July 2026, the contractor SEPCO3 said in October, with no date published for Unit 1.

What It Costs, and What Is Not Known
KenGen has not published an audited final cost for Olkaria I, though funding for the rebuild was put at over KSh 15 billion (Kenyan shillings, about US$115 million at the market rate of 130 per dollar on 25 November 2026) at the 25 November event. Across all its projects, KenGen invested KSh 15.5 billion (about US$119 million) in the year to 30 June 2026, with Olkaria I the centrepiece, the company said at the October meeting.
Frank Konuche, KenGen’s board chairman, spoke of the trade-off at that meeting. “Balancing shareholder returns, investment and debt reduction is essential to the lasting strength of the business,” he said.
The contractor pointed to the limits of working inside an old plant. “With a rehabilitation project, much of the existing structure has to remain, so you have to find solutions within the space and layout already available,” Zhang Yang, SEPCO3’s deputy project manager, said in an interview published on 30 October 2026.
How Much It Adds for Kenya
Kenya’s peak demand reached a record 2,514.28 MW on 29 June 2026, up 198 MW in a year, according to the 2025/26 statistics report of EPRA (Energy and Petroleum Regulatory Authority, the power regulator), released on 29 September 2026. Njenga put peak demand at 2,549 MW at the October meeting.
By our calculation, dividing the 18.3 MW gain by EPRA’s 2,514.28 MW peak, the rebuild adds 0.7% to Kenya’s peak needs. It covers about 9% of one year’s growth in peak demand.
KenGen still carries the grid. It supplied 8,975 gigawatt-hours (GWh) in the year to 30 June 2026, the company reported in October, which by our calculation is 57.2% of the 15,692.81 GWh that EPRA counted for the same year.
The steam field matters more than one plant. KenGen said on 25 November that fertiliser maker Kaishan, an investor at Olkaria’s Green Energy Park, an industrial zone beside the wells, would need about 165 MW of geothermal power, about nine times the gain at Olkaria I.
“This cannot be a resort city when we don’t have good drainage clean up and a good environment,” Simon Wakaba, a local youth leader, said at the same event on 25 November. We found no independent energy analyst commenting on the rebuild within the last 30 days.
What It Rules In and Out
In our reading, the rebuild rules in a longer life for the plant, more than 25 years by KenGen’s aim. By our calculation, it does not on its own ease Kenya’s supply squeeze.
In our reading, the next real capacity has to come from new plants such as Olkaria VII, a planned 80.3 MW KenGen station in the same field. KenGen’s grid target for it is June 2027, as reported in June 2026.
What to Watch
Monday 7 December 2026: President Ruto is due to commission Olkaria I; a final cost is the figure to look for. Monday 1 February 2027: Ronoh Kibet Charles, now KenGen’s general manager for commercial services, takes over from Njenga as managing director, KenGen announced in October 2026.
June 2027: the grid target for Olkaria VII. Around September 2027: EPRA’s next annual statistics report will show whether peak demand again rose by about 200 MW.
Related coverage: KenGen Seeks Investors for 5,540 Megawatts · KenGen Olkaria Licence Flaw Unfixed 18 Years
More: Kenya news
Frequently Asked Questions
Does the rebuild solve Kenya’s power needs?
No. By our calculation the 18.3 MW gain equals 0.7% of Kenya’s record peak demand of 2,514.28 MW, set on 29 June 2026, according to EPRA. The main gain is a longer plant life.
What is geothermal power?
It is electricity made from steam heated by hot rock deep underground, drawn up through wells in the Rift Valley. The steam spins turbines that drive generators.
Why does the plant’s age matter?
Olkaria I has run for more than four decades, and KenGen’s aim for the rebuild is to extend its life by more than 25 years. New turbines and generators replace equipment that ran for over four decades.
Sources: KenGen, Olkaria I Units 1, 2, 3 Rehabilitation Project page (https://www.kengen.co.ke/projects/olkaria-1-units-1-2-3-rehabilitation-project/), read 25 November 2026; Peter Njenga and Simon Wakaba, remarks in Naivasha, 25 November 2026 (Kenya News Agency; Citizen Digital; Business Today Kenya); KenGen annual general meeting, 29 October 2026 (Green Building Africa, 4 November 2026; ThinkGeoEnergy, 30 October 2026); EPRA, 2025/26 Energy and Petroleum Statistics Report, 29 September 2026 (Kenya News Agency, 30 September 2026); KenGen statements on the closure, 21 May 2023, and on contractors, 19 March 2024 (The Star); KenGen on its incoming managing director, 24 October 2026 (Citizen Digital); ThinkGeoEnergy, 18 June 2025 and 12 June 2026; market rate USD/KES, 25 November 2026.
This article was produced by The Rio Times’ automated AI newsroom. Editorial responsibility: Matthias Camenzind, Publisher and Editor-in-Chief. The Rio Times also runs Ask Rio Times, which answers from 100,000+ of our own articles, the daily Latin America Power Map, and prediction-market odds on elections and markets.. How we use AI · Report an error